⁂ L. Rhodes on Nostr: Better than no fine at all, I guess: but prior reporting says these are Bergen gas ...
Better than no fine at all, I guess: https://www.theguardian.com/environment/2026/sep/25/new-jersey-fines-datacenter-unpermitted-generators but prior reporting says these are Bergen gas turbines: https://www.theguardian.com/environment/2026/aug/27/new-jersey-vineland-datacenter-permits which range from 1.4MW–11.8MW/engine: https://www.bergenengines.com/on-land/ and going by these industry numbers: https://uspeglobal.com/articles/gas-turbine-epc-costs-2026/ that puts DataOne spending $97.7M–$1.6B on its 62 temporary turbines, so losing $1.1M is like losing use of one turbine temporarily, and they don't even have to stop for another 45 days.